A matrix indicating the order of precedence type 1 and 2 between the activities (Default=matrix(0)). If value \((i,j)=1\) then activity \(i\) precedes type \(1\) to \(j\), and if \((i,j)=2\) then activity \(i\) precedes type \(2\) to \(j\). Cycles cannot exist in a project, i.e. if an activity \(i\) precedes \(j\) then \(j\) cannot precede \(i\).
prec3and4
A matrix indicating the order of precedence type 3 and 4 between the activities (Default=matrix(0)). If value \((i,j)=3\) then activity \(i\) precedes type \(3\) to \(j\), and if \((i,j)=4\) then activity \(i\) precedes type \(4\) to \(j\). Cycles cannot exist in a project, i.e. if an activity \(i\) precedes \(j\) then \(j\) cannot precede \(i\).
duration
vector with the duración for each activities.
References
burke
Burke, R. (2013). Project management: planning and control techniques. New Jersey, USA.